Nov 11


This week was mainly devoted to the sub-trades getting the concrete main floor poured.  Very little was done with the framing since most of ort guys were off for the annual male bonding week.  As is traditional in North country at this time of year, most of our guys were off to their "hunt camp". 

Nature even co-operated by giving them our first snowfall.  The snow only stayed on the ground for a few days but it set the tone.


Before leaving they did get the sand under the floor compacted and the SM Styrofoam insulation in place for the plumber and the heating guys to install the mesh re-enforcement and the tubing for the in-floor heating.


On Friday the concrete was poured and levelled ready for the main floor interior finishing to come.






 Meanwhile the stonemason, Don, was busy installing the cultured stone to the front wall deck.
  