We ran out of shakes needed to complete the gable below and it will be a few weeks before the rest arrives but the rest of the siding is done and most of the soffit and fascia as well.
There was a lot of discussions and design changes to the sun room to created even openings on each side and meet all of Mike's design criteria. Everything is now firmed up and the cedar for the interior walls and for the window framing has been ordered.
The framing of the sun room has started
The stone mason has done as gone as far as he could on the front. He has to wait until the sun room is completed before he can complete the main floor (see second photo)
The tile man has completed the tiles in the upstairs bathroom and they look very good